Internal
Summer 2012
Sellaness
Malakoff built the ‘Brenda’, a 16.2m steel landing craft for internal use at Sellaness for the SVT Jetty Maintenance Contract.
The vessel was built in 2012 at Malakoff’s main base at North Ness, Lerwick, then transpThe vessel was built in 2012 at Malakoff’s main base at North Ness, Lerwick, then transported by road to Sellaness where the vessel was launched and put into service.orted by road to Sellaness where the vessel was launched and put into service.
The Brenda is a working barge that is based at Sellaness, the vessel is used as a working platform to carry out blasting/painting works. The vessel was launched in 2012, going into service at Sellaness. The vessel was originally fitted with a Tico crane and a hydro master unit.
In 2015, the vessel underwent a major refit, including the installation of inboard engines and the repositioning of the crane. This resulted in an increased deck area at the raft end of the work barge.